Technical Specification — Replace busway with 800-1000 A and new tap-off units

Reference Project (synthetic) · hall DH-02 · issued 2026-09-14 · ref REF-TND-01

Project
Reference Project (synthetic)
Hall
DH-02
Constraint relieved
Busway ampacity
Sized for
62 racks
Responses due
as agreed
Contact
—
Duties in this document are derived from a capacity model of this hall. They are modelled values, not measurements of installed plant, and each one names the constraint it came from.

1. Purpose

This package procures the works required to relieve Busway ampacity in hall DH-02. In the capacity model for this hall that constraint is what limits deployable rack count; relieving it moves the hall from 12 to 22 racks, and it is part of a programme that reaches 62 racks in total.

Duties in section 3 are sized for the end state of 62 racks of NVIDIA GB300 NVL72 — the hall this relief is part of delivering — not for the 10 rack(s) this single step unlocks on its own. Nobody buys plant for a marginal rack.

In the capacity model this step moves the hall from 12 to 22 racks; the full ladder reaches 62.

Every numeric requirement is derived from the capacity model and names the constraint it came from. Nothing here specifies a make or a model: we state the duty and the interfaces, the supplier proposes the equipment, and we take no margin on it.

The budget figure is our modelled estimate, not a price. It is stated so the client can see whether a response is in the right universe, and it carries its own evidence class.

Modelled budget for this relief
450,000 [225,000–900,000] EUR (E0)
Limited by: Our estimate, not a price. Stated so a response that is in the wrong universe is visible immediately.
Modelled lead time (assumed lead time, not a date)
36 [24–52] weeks (E0)
Limited by: assumed lead time, not a date (E0): what the capacity model assumed, not a quotation or a commitment. A response that differs materially moves the energisation date.
EVIDENCE DISCLOSURE: the duties in section 3 are derived from a capacity model built partly on library defaults and assumed inputs, not on a measured survey of this hall. The claim kinds still below the evidence required for an issued deliverable are: capex, cooling performance, electrical capacity, schedule (lead times). These duties are sufficient to obtain comparable, competent quotations and to see which supplier moves the energisation date. They are NOT sufficient on their own to raise a purchase order for long-lead plant: confirm the governing figures against site measurement first. The study's evidence appendix names exactly which ones those are.

2. Scope of supply

Included in this package:

Explicitly excluded. Listed rather than omitted, because an unstated exclusion is a gap somebody discovers on site:

2A. Site conditions and assumptions

Every duty in section 3 is quoted at these site conditions. Each numeric requirement in section 3 is derived from the constraint named in its 'From constraint' column, and these conditions are the model inputs those constraints used. A condition the client did not supply is printed as 'not supplied: assumed ...' with its evidence class; it is not a measurement and is not silently defaulted. A responder who has better data for any line shall say so in the response.

RefConditionValueStatusBasis
SC-01Design ambient dry bulb (summer)34 degC (E3)suppliedsupplied by the client (not measured or surveyed by us)
SC-02Design ambient wet bulb (summer)21 degC (E5)suppliedsupplied by the client (not measured or surveyed by us)
SC-03Facility-water supply temperature (existing plant)6 degC (E5)suppliedsupplied by the client (not measured or surveyed by us)
SC-04Technology-loop (TCS) supply target30 [27–32] degC (E0)assumednot supplied: assumed 30 degC (E0)
SC-05Site altitudenot modellednot modellednot supplied: the capacity model has no altitude input, so no altitude derating of air-cooled plant, motors or electrical equipment has been applied to any duty. Responders shall quote at the site altitude the client confirms and state it.
SC-06LV distribution voltage400 V (E5)suppliedsupplied by the client (not measured or surveyed by us) · 3-phase
SC-07Supply frequencynot modellednot modellednot supplied: the capacity model has no frequency input. Responders shall state the frequency they have assumed for the equipment quoted.
SC-08Site power factor0.97 (E3)suppliedsupplied by the client (not measured or surveyed by us)
SC-09Rack power basis: NVIDIA GB300 NVL72135 [132–142] kW (E0)libraryper-rack total TDP from the platform library, used for every electrical and thermal duty (utilisation is not applied to a duty)
SC-10Liquid heat-capture fraction: NVIDIA GB300 NVL720.9 [0.85–0.92] (E0)libraryplatform library figure; the remainder is residual air load per rack
SC-11Redundancy, transformer bank TX-A/BN+1 on 3 unitssuppliedsupplied by the client
SC-12Redundancy, UPS bank UPS-1N+1 on 6 unitssuppliedsupplied by the client

Values carry their unit and evidence class (E0 assumed ... E7 observed). 'library' is a platform figure; 'not modelled' means the engine has no input for the condition and has applied no derating for it.

Inputs to the capacity model that were assumed rather than supplied (each is an assumption at evidence class E0 unless it states otherwise):

3. Technical requirements

Obligation words carry their usual tender meaning: shall — non-compliance disqualifies the response; should — scored, not disqualifying; may — stated for context.

RefClauseObl.ValueFrom constraint
E-10Busway continuous ampacityshall1,990 A (E3)busway_ampacity
E-11Phasing and outageshall—busway_ampacity
E-12Tap-off provisionshall—busway_ampacity
C-01Price basisshall—commercial
C-02Validityshall—commercial
C-03Response scheduleshall—commercial

Every numeric requirement names the constraint it was derived from. A requirement nobody can trace back to a physical limit is one somebody invented.

**E-10 — Busway continuous ampacity** (shall). Each busway run shall have a continuous ampacity not less than the figure stated, at the hall's design ambient and installed configuration.

Required
1,990 A (E3)
Limited by: 62 racks at 135 [132–142] kW (E0) over 8 run(s) at 400 V (E5), three phase, power factor 0.95, derated to the site's 0.8 (E3) continuous limit. Installed: 400 A (E5).

*Verification:* Type test certificate to the applicable standard, with derating basis stated.

**E-11 — Phasing and outage** (shall). The programme shall allow replacement run by run with the hall in service. The response shall state the outage window per run.

*Basis:* Live tenancy in the hall during the works.

*Verification:* Method statement and programme.

**E-12 — Tap-off provision** (shall). Busway shall accept tap-off units at the density required by the rack pitch stated in the response schedule.

*Basis:* Hall aisle configuration; 62 positions to be fed.

*Verification:* Layout drawing.

**C-01 — Price basis** (shall). Prices shall be delivered and installed, excluding VAT, in EUR, with exclusions listed separately.

*Basis:* Comparability. Four quotations on four bases cannot be evaluated.

*Verification:* Completed response schedule.

**C-02 — Validity** (shall). Prices shall remain valid for not less than 60 days.

*Basis:* The evaluation and approval cycle on a capital item of this size.

*Verification:* Stated on the quotation.

**C-03 — Response schedule** (shall). The response schedule in section 6 shall be returned completed. An incomplete schedule will not be evaluated.

*Basis:* Every figure in it feeds a comparison the client can check. A bid that answers a different question cannot be compared with one that answers this one.

*Verification:* Returned document.

4. How responses will be evaluated

Price is one criterion of five. The item being bought exists to unlock compute on a date: a response that is cheaper and materially slower is the expensive one, and the weighting says so.

RefCriterionWeightWhat moves it
C1Compliance with the mandatory duty35%Every 'shall' requirement met, at the site conditions stated. A duty quoted at a reference condition rather than at ours scores nothing.
C2Delivered programme30%Weeks to site and to energisation, and which long-lead item governs. Assessed against what the item does to the energisation date.
C3Price20%Delivered capex, and price per kW actually unlocked rather than price per unit of equipment.
C4Installation in a live hall10%Outage duration per run or per unit, and the method statement.
C5Evidence quality5%Test certificates and selection outputs at our conditions, rather than datasheets at reference conditions.

Weights total 100.

A response that does not meet every 'shall' requirement is not ranked above one that does, whatever its price. That ordering is the entire point of a mandatory requirement.

5. Instructions to responders

6. Response schedule

Return these figures in these units. They feed a comparison the client can check line by line, which is only possible if every response answers the same question.

FieldUnitRequiredNote
Delivered price, excluding VATEURyesDelivered and installed. State exclusions separately.
Weeks from order to delivered on siteweeksyes
Weeks from delivery to energisedweeksno
Outage required per unit or per runhoursno
Duty achieved at the site conditions statedkW or AnoAt OUR conditions. A figure at a reference condition is not a bid.
Price validitydaysno

Machine-readable template: `gridforge spec … --template` writes a JSON file with these keys, which `gridforge bids` reads back.

Appendix A — Assumptions, provenance and validation status

Every number in this report carries an evidence class. The class of a computed number is never higher than the weakest of its inputs, so a model applied to measured data yields a modelled number and never a measurement.

ClassMeaning
E0assumed
E1modelled
E2simulated
E3estimated
E4validated against test data
E5supplied by the client (not measured or surveyed by us)
E6field-validated
E7observed in operation

E5 means supplied by the client — a declared rating, contract term or design value, or the client's own data as given. It is not a measurement we made, and it has not been verified by a site survey.

A.1 Assumptions relied upon

A.2 Sources

A.3 Provenance of headline quantities

QuantityEvidenceModelDigest
busway and tap-off works, per runE0costs.scaled_relief8bca5c542732
busway and tap-off lead timeE0input74ff17170551
summer design dry-bulbE3input7312d718f36d
summer design wet-bulbE5input95eb471b48b2
plant chilled-water supply temperatureE5input782cb160ee30
TCS supply temperature design pointE0input1dc1aaf81e33
LV distribution voltageE5input064883d0ef56
site power factorE3input9083b4d7b27e
GB300 NVL72 rack TDPE0inpute6476e7cd728
GB300 NVL72 liquid heat capture fractionE0inpute205b1f86e3c
required busway ampacity per runE3spec.busway_ampacity584d4571c5b5
required busway ampacity per runE3spec.busway_ampacity584d4571c5b5
Issued by GridForge AI on behalf of the client. We specify duty and interfaces only. We name no make or model, quote no equipment and take no margin on hardware.
Generated 2026-09-14 by the GridForge-AI envelope engine.